Project:- Blackwall Place, Building 2,  Canary Wharf, Fit-Out

Market Sector:- Commercial

Commercial Ductwork Contractors

Client   
Canary Wharf Group

Main Contractor
Canary Wharf Contractors Ltd

Design Consultant
Hilson Moran

Cost Consultant
Canary Wharf Contractors Ltd

Sub-Contract Value - £5.8 Million

Sub-Contract Programme –  21 months
covering shell & core
and fit out activities 



Project Description

BP2 is a large prestigious and unique new office building, 14 storeys plus 3 basement levels, constructed on reclaimed dockland in Canary Wharf to be leased by JP Morgan Chase.

Scope of Services – (Fit - out)

Having successfully completed the base build shell and core airside package ahead of program and on budget ASM, having competitively tender the fit out package, were successful in being appointed for the works. This included all the primary air ductwork and connecting to plant and equipment.

The combined program for Shell and Core plus fit-out was 21 months

pdf download as pdf

ASM Engineering Ltd - 74 Wilbury Way - Hitchin - Hertfordshire - SG4 0TP
Tel: 01462 477360 - Fax: 01462 477361 - E-mail: sales@asmeng.co.uk
Ductwork Contractors - Airside Design & Installation - Project Management - Commissioning - Private Finance Initiatives (PFI) free hit counter